Phase I and II of the three-phased project was performed while the Civic Center facility was occupied and in full operation. Phase I of the project consisted of the complete removal of existing roofing and plywood sheathing. Structural upgrades were then made to the existing roof framing, followed by the complete replacement of the roof. Phase II consisted of the addition of four structural steel brace frames.
ISI conduct special inspection and materials testing of the structural foundation and welding –- including concrete, structural steel, field, shop welding, and rebar inspection services.

  • Connector.

    Duration

    2012

  • Connector.

    Construction Value

    $200K

Share this Project